F0 Β· Concept
currently active Β· Q2 2026
F1 Β· NEXUS ORIGO SPFD
Q3 β Q4 2026 Β· ~5 mo
SPFD β
Platform / Partner LOIs
Q3 2026 β Q1 2027
F2 Β· Bankable Feasibility
Q1 β Q4 2027 Β· ~9β10 mo
F3 Β· FEED + ESIA
Q4 2027 β Q4 2028 Β· ~12 mo
F4 Β· Detailed Design + Financial Close
Q4 2028 β Q1 2029
F5 Β· Construction
Q2βQ3 2029 β Q4 2033 Β· ~4.5 yr
F6 Β· Commissioning + Operations
Q1 2034 β Q2 2035 β